We develop, manufacture, and operate an industrial-scale pyrolysis system to produce certified biochar. Located and operating in Ecuador, ready to deploy projects and pyrolisys systems in the region.
Technical Specifications
Technology Type
slow_pyrolysis
Process Type
Continuous
Biomass Throughput
—
Biochar Throughput
—
Heat Output
150 - 150 kW
Steam Output
—
Electrical Output
—
Expected Lifetime
10 years
Operators Needed
2
Lead Time
—
Remote Monitoring
—
Carbon Credits
—
Feedstocks & Co-Products
Acceptable Feedstocks
Production Co-Products
Additional Information
Delivery Regions
Global
Reliability & Downtime
Nina reports more than 800 operational hours. The technical sheet states one to two people per shift. No measured uptime percentage, downtime rate, or fleet count was provided.
Maintenance & Servicing
Financial-model reactor price is $210,000 per TTD unit and includes installation by the Nina Energy team. The model prices an optional solar/forced-air dryer at $45,000 per reactor. Its 10-year equipment useful life and annual maintenance assumption of 3.5% of combined reactor and dryer CAPEX are modeling assumptions rather than stated warranty terms. For one $210,000 reactor plus one $45,000 dryer, that assumption equals approximately $8,925/year.
Pressure Consistency
—
Software Integration
Published electrical consumption is 8.83 kWh, but the measurement period or functional unit is not specified, so no structured electricity quantity is inferred. Nina reports 150 kWth of excess recovered heat and describes the system as energy self-sufficient for drying and steaming, eliminating LPG or diesel for those uses.